Hi Gurus,
I posted the same question some days ago, but i described a problem with reference about factory calendar. I better understand the problem, if you help me in this case:
I analyzed MD04, at given time show exception message 64, production finish date in this case is saturday, but my factory calendar not consider saturday and monday as workday . Why it happens?
In the first situation why exception message 64 is show?
In the second situation why consider saturday and monday as workday?
Premise:
In material master MRP2
In-house production =0
GR Processing Time = 0
"Standard" SchedMargin key = 000
Planned Deliv. Time = 0
in work center
Start 7:12AM finish 2:16 AM capacity 13,65
* Capacity is ok
Routing
Machine 0,115 Hour - PP03
My customer has adopted it because time is too small to produce, the to do everything on the same day all itens
Regards
Leandro