Error in component quantity while exploding a multi level bom cs12

$
0
0

Hi,all

When I am trying to explode a multilevel bom by CS12 I am getting an issue.
During explosion if I wont give Required quanty SAP considers it as a base quantity and accordingly it will display the component quantity for the header material.If we give quantity as 10 then it will multiply the base quantity with 10 and sap will show the component quantity after execution.
My issue is when I am giving required quantity 1 to 1000 ther is no change in the component quantity where as when I gave required quantity as 10000 it is giving me the correct result.
My question is why ther is no change of component qty when i gave 10 to 1000