Hi Experts,
What will be the correct MRP data settings?
Here’s the scenario we are attempting to satisfy.
Lets say we have inventory= 10
Data settings:
Min to reorder = 1
Max allowed in inventory= 10
Assume there’s an order reservation for 1-10 parts. MRP generates no PRs.
Assume there’s an order reservation for 10 or more – MRP generates PR to satisfy the order reservation plus orders 10.
I’ve attempted to do VB, but VB only generates once the inventory order falls below reorder point. I’ve attempted to do a VB with lot size HB with a max, it still didn’t work.
Please advice, which data setting will satisfy this requirement?
With Warm Regards,
Sayan